November 11, 2026

Delays in 25 Major Projects Push Costs Up by ₹2.11 Lakh Crore; 1,853 Projects Face Cost Overruns

New Delhi/Alive News: Delays in major infrastructure projects across the country have added a significant financial burden on the government. According to the Centre’s October 2026 PAIMANA report, the estimated cost of 1,853 ongoing projects has increased by ₹3.22 lakh crore compared with their original budgets.

The 25 projects facing the highest cost overruns account for ₹2.11 lakh crore of this increase, nearly 65% of the total escalation. The additional expenditure could have been used to build more than 4,200 schools at an estimated cost of ₹50 crore each or over 1,400 hospitals costing ₹150 crore each. It could also have funded two projects similar to the Delhi-Mumbai Expressway.

Railway and Hydropower Projects Among the Most Delayed

Project delays are also affecting infrastructure development. The Hubballi-Ankola railway line in Karnataka is among the worst-affected projects. Originally scheduled for completion in March 2005, its deadline has now been extended to March 2030, marking a delay of 25 years.

Several hydropower projects, including Subansiri and Tapovan-Vishnugad, have also faced delays of more than 16 years.

However, the report indicates that not all projects are facing major setbacks. Around 1,360 projects are progressing either on schedule or with delays of up to two years.

Why Are Projects Getting Delayed?

Former PWD chief Hariom Sharma said changes in government priorities and delays in fund allocation can affect long-term projects. Administrative hurdles, land acquisition and environmental and forest clearances are also among the factors affecting implementation.

He added that improved monitoring and coordination among government departments could help reduce delays and prevent further cost escalation.